docs(openup): migrate WI-1 artifacts from unversioned project-top docs/

work-items.md (project-management/), design-wi-1-injectable-rng.md
(analysis-design/), test-report-wi-1-injectable-rng.md (test/) move into
the canonical OpenUP home per the 2026-10-03 decision reversal. Verbatim,
no content changes; project-top docs/ husk removed.
This commit is contained in:
Jan-Peter von Hunnius 2026-10-03 17:18:04 +02:00
parent 4798f55660
commit 2343d5e154
3 changed files with 141 additions and 0 deletions

View file

@ -0,0 +1,11 @@
# Skara Brae — Work Items List
| # | Issue | Work Item | Iteration | PSP level | Est. N (LOC) | Act. N (LOC) | Est. time (min) | Act. time (min) | Status |
|---|-------|-----------|-----------|-----------|--------------|--------------|-----------------|-----------------|--------|
| 1 | skara-brae-server#1 | Injectable RNG (plan item #8) | I1 | PSP1.0 | 35 (pred. 42, PI 37–73) | **41** | 105 (PI 75–135) | **90** | **Done** — both actuals inside 70% PI (size −2.4%, time −14%) |
| 2 | skara-brae-server#2 | Architecture cleanup + OpenUP work set (plan item #7) | I1 | PSP1.0 | 660 (pred. 951, PI 607–1295) | — | 620 (PI 455–785) | — | Open — typed responses, run_adventure extraction, constants, unwrap, fmt baseline; full OpenUP work set (Vision, UC, Suppl. Specs, A&D, Test Cases) |
Notes:
- Estimates filled during PLN (PROBE); actuals during PM postmortem.
- Iteration I1 = first Skara Brae iteration (starts with this WI).
- OpenUP work products live at the project top folder (`docs/openup/`), not per-repo.