# Skara Brae — Work Items List
| # | Issue | Work Item | Iteration | PSP level | Est. N (LOC) | Act. N (LOC) | Est. time (min) | Act. time (min) | Status |
|---|-------|-----------|-----------|-----------|--------------|--------------|-----------------|-----------------|--------|
| 1 | skara-brae-server#1 | Injectable RNG (plan item #8) | I1 | PSP1.0 | 35 (pred. 42, PI 37–73) | **41** | 105 (PI 75–135) | **90** | **Done** — both actuals inside 70% PI (size −2.4%, time −14%) |
| 2 | skara-brae-server#2 | Architecture cleanup + OpenUP work set (plan item #7) | I1 | PSP1.0 | 660 (pred. 951, PI 607–1295) | **1833** | 620 (PI 455–785) | **~171** | **Done** (pending human gates) — size +42% OVER UPI, time 72% UNDER LPI; 22 defects, 100% pre-compile; gates green, 71/71 tests |
Notes:
- Estimates filled during PLN (PROBE); actuals during PM postmortem.
- Iteration I1 = first Skara Brae iteration (starts with this WI).
- Canonical OpenUP home since WI-2: this repo (`skara-brae-common/docs/openup/`); roadmap.md stays at the project top folder.