skara-brae-common/docs/openup/project-management/work-items.md
Jan-Peter von Hunnius 2343d5e154 docs(openup): migrate WI-1 artifacts from unversioned project-top docs/
work-items.md (project-management/), design-wi-1-injectable-rng.md
(analysis-design/), test-report-wi-1-injectable-rng.md (test/) move into
the canonical OpenUP home per the 2026-10-03 decision reversal. Verbatim,
no content changes; project-top docs/ husk removed.
2026-10-03 17:18:04 +02:00

11 lines
1 KiB
Markdown
Raw Blame History

This file contains ambiguous Unicode characters

This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.

# Skara Brae — Work Items List
| # | Issue | Work Item | Iteration | PSP level | Est. N (LOC) | Act. N (LOC) | Est. time (min) | Act. time (min) | Status |
|---|-------|-----------|-----------|-----------|--------------|--------------|-----------------|-----------------|--------|
| 1 | skara-brae-server#1 | Injectable RNG (plan item #8) | I1 | PSP1.0 | 35 (pred. 42, PI 37–73) | **41** | 105 (PI 75–135) | **90** | **Done** — both actuals inside 70% PI (size −2.4%, time −14%) |
| 2 | skara-brae-server#2 | Architecture cleanup + OpenUP work set (plan item #7) | I1 | PSP1.0 | 660 (pred. 951, PI 607–1295) | — | 620 (PI 455–785) | — | Open — typed responses, run_adventure extraction, constants, unwrap, fmt baseline; full OpenUP work set (Vision, UC, Suppl. Specs, A&D, Test Cases) |
Notes:
- Estimates filled during PLN (PROBE); actuals during PM postmortem.
- Iteration I1 = first Skara Brae iteration (starts with this WI).
- OpenUP work products live at the project top folder (`docs/openup/`), not per-repo.