Skara Brae — Work Items List

# Issue Work Item Iteration PSP level Est. N (LOC) Act. N (LOC) Est. time (min) Act. time (min) Status
1 skara-brae-server#1 Injectable RNG (plan item #8) I1 PSP1.0 35 (pred. 42, PI 37–73) 41 105 (PI 75–135) 90 Done — both actuals inside 70% PI (size −2.4%, time −14%)
2 skara-brae-server#2 Architecture cleanup + OpenUP work set (plan item #7) I1 PSP1.0 660 (pred. 951, PI 607–1295) 1833 620 (PI 455–785) 201 Done, merged & closed 2026-10-05 — size +42% OVER UPI, time UNDER LPI (both PIs missed, opposite directions — calibration: agent-class data); 24 defects, 100% pre-compile; gates green, 71/71 tests; EA model built incl. XMI backup; EA session time deliberately unbooked

Notes:

  • Estimates filled during PLN (PROBE); actuals during PM postmortem.
  • Iteration I1 = first Skara Brae iteration (starts with this WI).
  • Canonical OpenUP home since WI-2: this repo (skara-brae-common/docs/openup/); roadmap.md stays at the project top folder.