1.2 KiB
1.2 KiB
Skara Brae — Work Items List
| # | Issue | Work Item | Iteration | PSP level | Est. N (LOC) | Act. N (LOC) | Est. time (min) | Act. time (min) | Status |
|---|---|---|---|---|---|---|---|---|---|
| 1 | skara-brae-server#1 | Injectable RNG (plan item #8) | I1 | PSP1.0 | 35 (pred. 42, PI 37–73) | 41 | 105 (PI 75–135) | 90 | Done — both actuals inside 70% PI (size −2.4%, time −14%) |
| 2 | skara-brae-server#2 | Architecture cleanup + OpenUP work set (plan item #7) | I1 | PSP1.0 | 660 (pred. 951, PI 607–1295) | 1833 | 620 (PI 455–785) | 201 | Done, merged & closed 2026-10-05 — size +42% OVER UPI, time UNDER LPI (both PIs missed, opposite directions — calibration: agent-class data); 24 defects, 100% pre-compile; gates green, 71/71 tests; EA model built incl. XMI backup; EA session time deliberately unbooked |
Notes:
- Estimates filled during PLN (PROBE); actuals during PM postmortem.
- Iteration I1 = first Skara Brae iteration (starts with this WI).
- Canonical OpenUP home since WI-2: this repo (
skara-brae-common/docs/openup/); roadmap.md stays at the project top folder.