skara-brae-common/docs/openup/project-management/work-items.md
Jan-Peter von Hunnius c92220b2a4
All checks were successful
build / build-test (push) Successful in 17s
docs(openup): WI-2 closed - merged into both mains, issue #2 done (final actuals)
2026-10-05 12:00:36 +02:00

11 lines
1.2 KiB
Markdown
Raw Permalink Blame History

This file contains ambiguous Unicode characters

This file contains Unicode characters that might be confused with other characters. If you think that this is intentional, you can safely ignore this warning. Use the Escape button to reveal them.

# Skara Brae — Work Items List
| # | Issue | Work Item | Iteration | PSP level | Est. N (LOC) | Act. N (LOC) | Est. time (min) | Act. time (min) | Status |
|---|-------|-----------|-----------|-----------|--------------|--------------|-----------------|-----------------|--------|
| 1 | skara-brae-server#1 | Injectable RNG (plan item #8) | I1 | PSP1.0 | 35 (pred. 42, PI 37–73) | **41** | 105 (PI 75–135) | **90** | **Done** — both actuals inside 70% PI (size −2.4%, time −14%) |
| 2 | skara-brae-server#2 | Architecture cleanup + OpenUP work set (plan item #7) | I1 | PSP1.0 | 660 (pred. 951, PI 607–1295) | **1833** | 620 (PI 455–785) | **201** | **Done, merged & closed 2026-10-05** — size +42% OVER UPI, time UNDER LPI (both PIs missed, opposite directions — calibration: agent-class data); 24 defects, 100% pre-compile; gates green, 71/71 tests; EA model built incl. XMI backup; EA session time deliberately unbooked |
Notes:
- Estimates filled during PLN (PROBE); actuals during PM postmortem.
- Iteration I1 = first Skara Brae iteration (starts with this WI).
- Canonical OpenUP home since WI-2: this repo (`skara-brae-common/docs/openup/`); roadmap.md stays at the project top folder.